Project | Sustainability- Chirapunchi BG - Peruvallur GP |
---|---|
Project Code | MLPGoK11209984 |
Type | Main project |
Funding Agency | GoK |
Category | Sustainability |
Type of scheme | Water Supply |
Scheme | 2215-01-102-80 |
Description | renovation and rehabilitation of source,pump house, tank and pipeline |
Status | Completed |
District | Malappuram |
Executing Office | RPMU Malappuram |
AS Amount (Rs) | 805000 |
AS Number | 2/1 |
TS Amount (Rs) | 530000 |
TS Number | TS/MT2/RPMU/MPM/SUS/18/2021-22 |
Total Bill Submitted (Rs) | 410063 |
Total Bill Paid (Rs) | 410063 |
Population Benefitted | 74 |
Capacity in MLD | 0.02 |
Actual Project Completion Date | 16 Mar 2022 |
Coverage | 370 |
Date of start of Project | 10/07/2021 |
---|---|
Scheduled date of Completion of the Project | 16 Mar 2022 |
Expected date of Completion | 16/03/2022 |
AS Date | 03 Nov 2020 |
---|---|
TS Date | 18 Nov 2020 |
Project Officers | View |
---|