Project | PACKAGE 1 |
---|---|
Project Code | MLPGoK021911123P1 |
Type | Package |
Main Project | Sustainability-Kannamparambu BG - Puzhakattiri GP |
Funding Agency | GoK |
Category | Sustainability |
Type of scheme | Water Supply |
Scheme | 2215-01-102-80 |
Description | SOURCE, PUMP HOUSE , PUMPING MAIN |
Status | Completed |
District | Malappuram |
Executing Office | RPMU Malappuram |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 500000 |
TS Number | MT/20/2019 |
Technical specification | NIL |
Contractor | HAMZA M.K (Mob: 9446158451) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/12/2020 |
---|---|
Scheduled date of Completion as per agreement | 12 Feb 2021 |
Expected date of Completion | 12/02/2021 |
TS Date | 25 Mar 2019 |
---|---|
Estimate Approval | 02 Jan 2021 |
NIT Approval | 09 Jan 2021 |
Tender Closing | 16 Jan 2021 |
Technichal Pre-Qualification | 22 Jan 2021 |
Price bid opening | 27 Jan 2021 |
Workorder Date | 01 Feb 2021 |
---|---|
NA | 05 Feb 2021 |
RPMU Malappuram |
Date: 14/10/2022 |
Work has been completed | 100% Completed
COMPLETED.
RPMU Malappuram |
Date: 20/06/2022 |
Work in progress | 97% Completed
FINAL AUDIT NOT DONE . TS AMOUNT IS ABOVE 500000..