PMS

Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

PACKAGE 1

Project PACKAGE 1
Project Code MLPGoK021911123P1
Type Package
Main Project Sustainability-Kannamparambu BG - Puzhakattiri GP
Funding Agency GoK
Category Sustainability
Type of scheme Water Supply
Scheme 2215-01-102-80
Description SOURCE, PUMP HOUSE , PUMPING MAIN
Status Completed
District Malappuram
Executing Office RPMU Malappuram
Agreement Number
Agreement Date
TS Amount (Rs) 500000
TS Number MT/20/2019
Technical specification NIL
Contractor HAMZA M.K (Mob: 9446158451)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/12/2020
Scheduled date of Completion as per agreement 12 Feb 2021
Expected date of Completion 12/02/2021

Processing Dates

TS Date 25 Mar 2019
Estimate Approval 02 Jan 2021
NIT Approval 09 Jan 2021
Tender Closing 16 Jan 2021
Technichal Pre-Qualification 22 Jan 2021
Price bid opening 27 Jan 2021

Approval Dates

Workorder Date 01 Feb 2021
NA 05 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

RPMU Malappuram
Date: 14/10/2022

Work has been completed | 100% Completed

COMPLETED.

RPMU Malappuram
Date: 20/06/2022

Work in progress | 97% Completed

FINAL AUDIT NOT DONE . TS AMOUNT IS ABOVE 500000..