Project | PACKAGE 1 |
---|---|
Project Code | MLPGoK102010039P1 |
Type | Package |
Main Project | Sustainability-Sahrudaya BG - Edarikode GP |
Funding Agency | GoK |
Category | Sustainability |
Type of scheme | Water Supply |
Scheme | 2215-01-102-80 |
Description | SOURCE , PUMPHOUSE |
Status | Completed |
District | Malappuram |
Executing Office | RPMU Malappuram |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 500000 |
TS Number | 24/2020-21 |
Technical specification | |
Contractor | HAMZA M.K (Mob: 9446158451) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 21/06/2021 |
---|---|
Scheduled date of Completion as per agreement | 05 May 2021 |
Expected date of Completion | Date is not specified |
TS Date | 14 Jan 2021 |
---|---|
Estimate Approval | 08 Mar 2021 |
NIT Approval | 15 Mar 2021 |
Tender Closing | 22 Mar 2021 |
Technichal Pre-Qualification | 29 Mar 2021 |
Price bid opening | 06 Apr 2021 |
Workorder Date | 06 Apr 2021 |
---|---|
NA | 13 Apr 2021 |
RPMU Malappuram |
Date: 14/10/2022 |
Work has been completed | 100% Completed
completed.
RPMU Malappuram |
Date: 22/07/2022 |
Work in progress | 95% Completed