PMS

Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Sustainaility-Panchami BG PulpettaGP

Project Sustainaility-Panchami BG PulpettaGP
Project Code MLPGoK092212832
Type Main project
Funding Agency GoK
Category Sustainability
Type of scheme Water Supply
Scheme 2215-01-102-80
Description Rehabilitation&Renovation
Status Completed
District Malappuram
Executing Office RPMU Malappuram
AS Amount (Rs) 875000
AS Number G.O.(Rt)No837/2022/WRD
TS Amount (Rs) 875000
TS Number TS/PC/RPMU/MPM/PULPATTA/SUS/01/2022-23
Total Bill Submitted (Rs) 500229
Total Bill Paid (Rs) 394030
Population Benefitted 145
Capacity in MLD 0.01
Actual Project Completion Date Date is not specified
Coverage 29

Packages

No. Project Name Location View
1 PUMPSET PANCHAMI PULPETTA RPMU Malappuram
2 Repair&Renovation of well,tank,Distribution RPMU Malappuram

No status have been added to this project

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/12/2022
Scheduled date of Completion of the Project 02 Nov 2023
Expected date of Completion 02/11/2023

Processing Dates

AS Date 17 Sep 2022
TS Date 30 Sep 2022

Other details

Project Officers View