Rain Water Harvesting and Ground Water Recharge Project - Erattayar GP

Project Rain Water Harvesting and Ground Water Recharge Project - Erattayar GP
Project Code IDKGoK062111240
Type Main project
Funding Agency GoK
Category Rain Water Harvesting and GWR
Type of scheme Others
Scheme 2215-01-102-80
Description Construction of 165 nos of Rain Water Harvesting Tank for individual Households in Erattayar GP, Idukki District
Status Completed
District Idukki
Executing Office RPMU Idukki
AS Amount (Rs) 12663000
AS Number KRWSA-PMU/152/2021-AC1(RC)
TS Amount (Rs) 12787000
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 Rain Water Harvesting and Ground Water Recharge Project - Erattayar GP RPMU Idukki

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Oct 2022 Construction of 165 RWH units completed RPMU Idukki
21 Jul 2022 53% of work completed RPMU Idukki
23 Jun 2022 39% of work completed RPMU Idukki
23 Jun 2022 RWH tank construction in progress RPMU Idukki

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 14/03/2022
Scheduled date of Completion of the Project 10 Aug 2022
Expected date of Completion 10/08/2022

Processing Dates

AS Date 25 Jun 2021
TS Date 16 Aug 2021

Other details